Hi,
I've recently started learning AMS 7.5 after briefly using 6.0 a couple of years ago for a very straightforward job.
This forum has been an invaluable tool for learning some of the intricacies of the program so sincere thanks to all of you who are so generous with comments, code and explanation.
The problem I'm trying to deal with at the moment is that I cannot get the little arrows either side of the calendar plugin to "fire" as anticipated. From the help file, it looks as though e_CurrMonthYear should be returned when a new month is selected by the arrows as well as the "hold down the left mouse button" method.
I see this was raised a year or so ago - http://www.indigorose.com/forums/showthread.php?t=18630 - and wonder if the bug (if that's what it is) has been sorted out and I'm just doing something wrong!
Any guidance would be very welcome.
Thanks
TopicTJ

Reply With Quote